Diamante Project

Client

CODELCO

Location

División el Teniente, Chile

Scope

Development of the basic and detailed engineering for underground mining.

Datos técnicos

  • 44 km of tunnels
  • 700,000 m3 of excavation
  • 60,000 m2 conditioned area
  • 1,800 tonnes of explosives
  • 1.5 km of railway
    • 8.3 MVA of installed power
    • 2.5 km of main access road
    • 10.7 million man-hours

More about the project